Completion of Daang Hari-SLEX link road moved to June

The opening of the P2.01-billion Daang Hari-South Luzon Expressway link is likely to be opened in June instead of this month.

Department of Public Works and Highways (DPWH) Undersecretary Rafael Yabut confirmed in a statement that the completion of the PPP toll road has been moved further to June.

Now known as the Muntinlupa-Cavite Expressway (MCX), the Daang Hari-SLEX link was the first PPP project auctioned off and awarded under the program. It was bagged by Ayala Corp. through AC Infrastructure Holdings Corp.

The project involves the construction of a new four-kilometer, four-lane toll road from the junction of Daang Reyna and Daang Hari in Las PiƱas and Bacoor, Cavite to SLEX through the Susana Heights Interchange in Muntinlupa, traversing the New Bilibid Prison (NBP) Reservation.

The proposed link-road would use the Susana Heights Interchange as exit and entry from north and south of SLEX and would include the construction of a new bridge or widening of the existing bridge crossing SLEX, as well as the expansion of the Susana Heights Toll Plaza.

In December 2011, the project was awarded to Ayala Group. It was supposed to be completed last June but it was delayed due to problems with interconnection to SLEX.


The conglomerate was looking at completing the project December last year after signing an agreement with South Luzon Tollway Corp. (SLTC) paving the way for the construction of the interchange linking the toll road to SLEX.

 

 